Pipe Replacement

Location:

Bowling Green, FL

Industry:

Phosphate

Client:

Mosaic

Product or Services Provided:

Mid-State Industrial Maintenance was awarded a project to remove an existing matrix box and replace it with 42” piping. Matrix material is highly abrasive and the requires proper material selection to ensure that it will last for the designed duration. The pipe was lined with 2” thick rubber and was installed while the plant was down. Mid-State estimated this project would be installed in 4 days and we completed the job ahead of schedule, on budget and, with no injuries.

Have Questions About Our Services?

We’re here to help and a specialist will contact you about your project.

or call
Scroll to Top